Rockson Engineering Limited, the company handling the Kaduna Power Plant, says four out of the eight turbines in the plant are completed and ready to be powered.

Mr Sunny Okwedi, the Project Manager of the company, said this on Sunday in Kaduna during an inspection of the project by the Minister of Power, Works and Housing, Mr Babatunde Fashola.

He said that the four completed turbines would not be switched on until the Power Control Motor (PCM) was installed with the switch yard commissioned.

He said that the engineering work on the project was 98 per cent completed, procurement 93 per cent and construction 76 per cent.